Market Intelligence / Paper No. 6

Planning factory capex before financial close: four ways to treat each cost line

A factory’s total cost and the money it needs on day one are different numbers. The second decides how much equity is needed at financial close and how large the first loan must be. With lenders cautious about new solar and battery plants, getting that number right matters more than ever. In one line-by-line review, carried out by a member of our team in a previous role, about a third of the day-one need could move without making the plant any smaller.

Financial close · 6 minute read · Version 2.0, 9 November 2026

Why day-one funding matters now

A factory that needs less money on day one, with a tested plan for the rest, is easier to finance.

Lenders have reason to be careful with new clean-tech factories. Enerdata estimates that the world could make 1,315 GW of solar modules in 2025 but installed 664 GW, so module factories ran at about half their capacity on average. In battery manufacturing, plans run well ahead of plants: in India, only 21.6% of the battery manufacturing capacity identified by Mercom is operating, and the rest is under construction or announced.

Europe offers a warning. Northvolt, the Swedish battery maker, raised about US$15bn but filed for bankruptcy in March 2025 after large order cancellations and difficulty scaling production.

So lenders test a new factory’s plan harder. Founders and CEOs need to show exactly how much money the plant needs on day one, how the rest will be paid for, and what happens if the ramp-up slips.

Who gains? Founders and CEOs who can show a lean, well-tested day-one plan. Who loses out? Projects whose capex lists mix day-one needs with later phases and ask lenders to fund everything at once.

  • ~49%Average utilisation of the world’s module factories in 2025Enerdata, Jul 2026
  • 21.6%Share of identified Indian battery manufacturing capacity that is operatingMercom, Oct 2026

Two different numbers

Splitting day-one needs from later phases changes the equity cheque, not the plant.

Capex means capital expenditure, the money spent on building and equipping a plant. The total project cost is the lender’s appraisal figure (in Indian banking, the “Cost of Project”). It includes hard capex (the plant and equipment), pre-operative expenses (costs before the plant starts running), interest during construction, contingency (an allowance for overruns) and a working-capital margin (the part of the plant’s running money funded as part of the project).

It is the figure in the project report that the lender reviews, and the one its loan approval refers to. In India these are the detailed project report and the sanction letter.

Day-one capex is what must be funded at financial close for the plant to start producing. Financial close is the point when the financing is signed and money can start to be drawn. Day-one capex covers the lines on the critical path to first output (the items production cannot start without), plus the contingency a lender insists on. Anything that can be built later, once there is revenue and a ramp-up (production rising towards full output) to point to, is not day one.

These usually sit outside day one: production lines for phase 2; test-lab items that an outside lab can handle for two years; interiors and second offices; software platforms for products not yet in the first offtake (the first agreed sales of the plant’s output); and simulators that a contractor already provides.

Keeping the two apart helps the board and the lender see when money is needed. A founder or CEO who negotiates the total cost down is arguing about the plant. One who separates day one from later phases is arguing about the size of the equity cheque. The debt–equity ratio, the size of the loan and the dilution before close (how far existing owners’ shares shrink as new equity comes in) all move with it.

Who gains? Founders and CEOs who split day-one needs from later phases and put in less equity at close. Who loses out? Founders and CEOs who present one undivided capex list and fund all of it up front.

Four ways to treat a cost line

Labelling every line with one of four approaches makes each trade-off visible.

Every change you can make to a cost line is one of four kinds. Label each line with one and the trade-offs become clear. Lines with only a “budgetary” estimate and no real quote are where the room to negotiate lies, and where lenders mark you down for being imprecise.

ApproachWhat it meansThe trade-offTypical examples
CorrectRemove mistakes: costs counted twice, quotes that newer ones have replaced, and items already in a contractor’s scope.None. It makes your numbers more credible to the lender.Old and new civil-works quotes both included; certification budgeted twice; a simulator the EPC (engineering, procurement and construction) contractor provides.
DeferBuild it later, in step with rising production volumes. Pay for it from operating cash or extra borrowing.Production must ramp up on plan. If it slips, the funding gap stretches.Phase-2 lines; environmental test chambers; software platforms for a second product.
Asset-lightRent, outsource or license instead of owning.A higher cost per unit, and you depend on a provider.External test labs; leased buildings; technology licensed rather than bought.
NegotiateGet new quotes, based on the real scope, for lines that have no quote or only a budgetary estimate.It takes effort and time, and some lines come back higher.Sheds and interiors; the high-voltage (HV) substation; technology fees charged per unit rather than as a lump sum.

What one line-by-line review found

Most of the gain came from timing, not from cutting the plant, so the plan depends on the ramp-up.

This was a line-by-line capex review for a storage manufacturing plant, carried out by a member of our team in a previous role. About 14% of the original Cost of Project was a double-count, with old and new figures both carried for civil works and certification. It was removed straight away. About 11% sat in civil-works lines with no quotes, where there was real room to negotiate. A technology fee moved from a lump sum to a price per unit, and part of its scope moved to local suppliers. Test-lab items the CEO had already marked “phase 2” were formally deferred. The day-one funding need fell by roughly a third, mostly through deferral. Plant capacity did not change, and moving spend later does not, on its own, reduce the total cost.

  • ~14%Of the original Cost of Project was a double-count, removed straight awayOne 2026 review, previous role
  • ~11%Sat in unquoted civil-works lines, with room to negotiateOne 2026 review, previous role
  • A thirdFall in the day-one funding need, mostly from deferral; plant capacity unchangedOne 2026 review, previous role

The financial model has to carry it

Deferral relies on early cash from operations, so the ramp-delay case decides whether lenders accept it.

Lenders do not approve a spreadsheet of savings. They approve a quarterly integrated model: one in which the profit and loss account, balance sheet and cash flow are linked, the balance sheet balances, debt payments show every quarter, and the lender can run its own stress cases (tests of what happens when things go wrong).

So the review produces two things. The first is the register: every cost line, its phase, whether it has a quote, and the approach proposed. The second is the model, which carries each phase into the three financial statements, the drawdown schedule (when loan money is drawn), the DSRA test and the covenant dashboard. The DSRA, or debt service reserve account, is cash set aside to meet loan payments. Covenants are the conditions in the loan that the borrower must keep to.

The what-if case that matters most is a delay in the ramp-up. Deferral lowers the equity needed at close by betting on cash from operations. If commissioning (getting the plant up and running) slips by two quarters, the deferred items and the loan payments fall due together. Debt-service cover (DSCR) is the cash available to pay the debt divided by the payments due. In the review described above, the ramp-delay case took debt-service cover from about 2.7× to 1.35×, against a covenant of 1.25×. Show the lender that case, and the cash buffer that survives it.

Who gains? Founders and CEOs who show lenders the delay case and the cash buffer that survives it. Who loses out? Plans that defer spending without testing what happens if production starts late.

  • ~2.7×Debt-service cover in the base caseOne 2026 review, previous role
  • 1.35×Debt-service cover in the ramp-delay caseOne 2026 review, previous role
  • 1.25×The covenant level the cover was measured againstOne 2026 review, previous role

What it means for each party to a factory project

Funding day one, with a tested plan for the rest, makes a factory easier to finance.

  • Founders, CEOs and CFOs. Fund what day one needs, not the whole plan up front, and prove the plan survives a slower ramp-up.
  • Equity investors. A smaller day-one need means less dilution at close. Check the trigger for each deferred item.
  • Lenders. Expect a register and an integrated model, not a list of savings, and test the ramp-delay case and the reserve account.
  • Technology partners. Fees per unit instead of lump sums ease day-one funding. Agree what is deferred, and who pays if the ramp-up slips.

What to do next: the steps to financial close

Six steps from a capex list to a loan approval.

  1. Reconcile the numbers. Match the capex in the model to the CEO’s vendor sheet, line by line: vendor, country, quote status and remarks. Remove double-counts first.
  2. Label each line. Mark each line as correct, defer, asset-light or negotiate, and write the trade-off next to it. The founder or CEO decides how far to go on each. Nothing is assumed.
  3. Split it into phases. Rebuild the capex schedule as day one and later phases. Note what triggers each deferred item: a volume reached, a certification gained or an offtake signed.
  4. Build it into the model. Carry the phases through the integrated model. Run the ramp-delay case. Size the DSRA and the contingency the lender will require.
  5. Know the order lenders follow. Lenders usually want an independent project report first, then their own credit approval; in India this often means the detailed project report, a credit rating and then sanction. Equity usually has to be in, or committed, before the loan is first drawn.
  6. Keep it on track. Review progress every week until close, with a named owner for each open quote. Keep the register up to date. After close, it becomes the way you control capex.

Words used in this paper

  • Capex: Capital expenditure: the money spent on building and equipping a plant.
  • Total project cost: The lender’s full figure for a project (in India, the Cost of Project): capex, pre-operative costs, interest during construction, contingency and some working capital.
  • Day-one capex: The money that must be funded at financial close for the plant to start producing.
  • Financial close: The point when a project’s financing is signed and money can start to be drawn.
  • Sanction: In Indian banking, a lender’s formal approval of a loan, set out in a sanction letter.
  • Asset-light: Renting, outsourcing or licensing something instead of owning it.
  • Commissioning: Getting a new plant up and running.
  • DSCR: Debt-service cover ratio: the cash available to pay the debt, divided by the payments due.
  • DSRA: Debt service reserve account: cash set aside to meet loan payments.
  • Covenant: A condition in a loan that the borrower must keep to, such as a minimum DSCR.

Figures were checked on 9 November 2026. The case figures are rounded and anonymised, and lenders’ terms vary. This is general information, not legal, tax or investment advice.

Sources

  1. Anonymised and rounded results from a 2026 capex review and financial-close readiness assignment, carried out by a member of our team in a previous role
  2. Enerdata, “The new global reality for PV module manufacturers” (22 July 2026): enerdata.net
  3. Mercom India, “India’s downstream battery storage manufacturing capacity reaches 86 GWh” (22 October 2026): mercomindia.com
  4. ESS News, “Northvolt files for bankruptcy in Sweden” (12 March 2025): ess-news.com
  5. General project-finance practice on project cost, debt-service reserve accounts and cover covenants; terms vary by lender

Talk to us

We can build the model, go through your capex line by line and get the project report ready for the lender's review.

Book a consultationOr write to us

The Bankability and Financial Close project: deliverables and fees

Version 2.0, 9 November 2026: retitled, rewritten in plainer language for a global audience, slides redesigned with a takeaway on every slide, and why it matters now added (factory overcapacity, unbuilt battery capacity and Northvolt’s bankruptcy). The case figures are unchanged. Version 1.3, 5 November 2026: the closing panel of the PDF and PowerPoint was aligned with the web page. Version 1.2, 4 November 2026: the review is attributed to a team member's previous role, and the funding point is stated more carefully. Version 1.1, 26 October 2026: the one-third figure is now stated as one case, and deferral is distinguished from cost reduction.

More papers: Registering solar modules under MCS · EU battery passport: what to have ready · India’s battery storage local-content rules · UK and EU trade deals with India: what changes for clean-tech · Bankability for solar and storage: Tier 1 and what lenders check

Register to download

You can read every Market Intelligence Paper online. Register once to download all six as PDF or PowerPoint.