What the two rules say
Battery projects under the new scheme will need twice the Indian content of earlier funded projects.
In late December 2025 the Ministry of Power set a rule for battery storage projects that receive viability gap funding (VGF), the government grant that makes these projects affordable. At least 20% of each project’s total cost has to be made or done in India. The order named only one component: energy-management software, the program that runs the battery plant, counts towards the 20% if it was developed in India. It said nothing about cells, packs, containers or battery-management systems.
On 4 November 2026 the Union Cabinet approved a new scheme. It sets aside ₹14,500 crore (₹145 billion) of VGF for 92 GWh of storage between 2026–27 and 2030–31: 60 GWh of pumped hydro, 30 GWh of batteries and 2 GWh of other technologies. Capacity will be awarded through tariff-based competitive bidding, and distribution companies can receive the funding for battery and pumped hydro projects. Battery projects under the scheme must have at least 40% domestic content. The Cabinet said the aim is to build battery manufacturing in India and cut imports, alongside the existing grants for cell factories. It also said India will need 411 GWh of grid-scale storage by 2031–32, counting pumped hydro.
The guidelines that will explain how the 40% is measured, and which parts count, had not been published as at 9 November 2026. We will update this paper when they are.
- 20%Minimum Indian content since December 2025; Indian software countsMinistry of Power
- 40%Minimum for battery projects under the new schemeUnion Cabinet, 4 Nov 2026
Why the volumes matter
Tens of gigawatt-hours of funded battery projects will need Indian content over the next five years.
The volumes are large. Earlier VGF schemes already support about 43 GWh of battery storage, about 31.6 GWh has gone out to tender since 2024, and the new scheme adds another 30 GWh. A growing share of India’s storage will have to be partly made in Indian factories.
Demand may grow beyond the funded schemes. In September 2026 the Central Electricity Authority published draft rules that would require new ground-mounted solar and onshore wind projects commissioned from July 2027 to have storage on site equal to at least 10% of their capacity, for at least two hours, rising to four hours from July 2029. Comments closed on 4 October 2026 and the rules are not yet final. The 40% rule is tied to the funding scheme, so whether it would reach that storage is not yet clear.
- 30 GWhBattery storage in the new schemeUnion Cabinet, 4 Nov 2026
- 411 GWhGrid-scale storage India needs by 2031–32, counting pumped hydroUnion Cabinet, 4 Nov 2026
How the 40% is measured
The base and the counting method decide whether a factory passes or fails.
Under the 20% rule, a developer could reach the target with Indian software, containers, wiring and services, and import the cells. Mercom points out that this is why the rule did little for Indian cell makers. 40% is harder. According to Mercom, battery systems made up more than half of the cost of a large storage project in the second quarter of 2026, and cells are a big part of that.
Three questions will decide how hard the new rule is. The first is the base. The 20% was a share of the whole project cost. The guidelines could keep that base, measure only the battery system, or name parts that must be made in India.
The second is how value is counted. India’s public procurement rules, set out in the Public Procurement (Preference to Make in India) Order, count local content as the value added in India. That is the price of the item, excluding domestic taxes, minus the value of its imported content including customs duty, as a share of the price. Since 2024 the rules also exclude licence fees and royalties paid abroad, and the cost of repackaging or rebranding imported products.
The third is how it is proved. Under the same rules, suppliers certify their own local content in the bid. For contracts above ₹10 crore, a statutory or cost auditor has to certify the figure, and a supplier that falls short can be penalised up to 10% of the contract value. The battery guidelines may set their own method, but this is the one Indian public buyers already use.
- Read the guidelines and the tender, not the press release. How the 40% is calculated, which parts count and what proof is needed will be in the scheme guidelines and the tender documents. Get them early and read them with your lawyers.
- Map your bill of materials now. List every part, where it is made, what it costs and who can certify it. The gap to 40% is the list of parts you would need to source in India.
- Start the evidence file. Suppliers’ certificates of origin and local content, cost records an auditor can follow and, for software, records showing what was developed in India.
Two ways the 40% could be measured
On the whole project, 40% is mainly an assembly target. On the battery alone, it becomes a cell target.
The base matters most. If the 40% is a share of the whole project, value added in India outside the battery, such as installation, civil works, software and power-conversion assembly, counts alongside Indian packs and containers. If it is a share of the battery system alone, that value no longer counts, and a large part of the battery’s value sits in the cells.
| Measured on the whole project | Measured on the battery system | |
|---|---|---|
| What counts | Everything: the battery, power conversion, software, civil works and installation. | Only the battery system: cells, packs, battery-management system and container. |
| Where Indian content can come from | Installation, civil works, software, power-conversion assembly, containers and Indian packs. | Indian packs, battery-management systems, containers and, most likely, cells. |
| Are Indian cells needed? | Possibly not, if most of the rest is made or done in India. | Hard to avoid, because cells are a large share of the battery’s value. |
| Who it suits | Integrators that assemble and install in India. | Makers with Indian cell supply or a cell technology partner. |
What each part of a battery system means for 40%
Most of a battery project outside the cells can already be sourced in India. Cells are the gap.
A storage project is more than its batteries. The cells sit inside modules and packs. A battery-management system watches over them. They are housed in containers with cooling and fire protection. Power-conversion equipment and transformers connect them to the grid, and energy-management software runs the whole plant. Around all of that are the civil works, installation and commissioning.
The table shows, for each part, how much is made in India today and what a 40% rule is likely to mean for it.
| Part of the system | Made in India today | Under a 40% rule |
|---|---|---|
| Cells | Very little so far; most cells are imported. | The hardest part to make in India. Indian cells are expected to cost 25 to 40% more than imports. |
| Modules and packs | Assembly capacity is growing fast. | Likely to be needed in India for most bids. |
| Battery-management system | Some Indian products; many are still imported. | An Indian-made system becomes more valuable. |
| Power conversion | Assembled in India; the power chips are imported. | Local assembly helps; the chips stay imported for now. |
| Energy-management software | Indian products exist, but the big plants so far mostly use foreign ones. | Still counts, and was the one part the December 2025 order named. |
| Containers, cooling, fire protection and wiring | Mostly made in India. | The easiest share, already counted by most bidders. |
| Civil works, installation and commissioning | Done in India. | Counts if the 40% is measured on the whole project cost. |
Where India’s factories stand
Indian content beyond assembly will be scarce and more expensive for several years.
Mercom puts India’s capacity for battery packs, containers and complete storage systems at about 86 GWh, without saying how much of it is already running. Much of India’s battery manufacturing is still to come: only 21.6% of all the capacity Mercom has identified is operating, and the rest is under construction or announced. Cells are only 8% of the capacity now operating. Under the government’s grant scheme for advanced cell factories (the production-linked incentive, or PLI), which aims to support 50 GWh, 6.4 GWh of supported capacity is running and 28.6 GWh is being built. New plants keep being announced, such as the 12 GWh battery storage factory planned by Premier Energies and RCT India.
Estimates of cell capacity differ with what is counted and when. Wood Mackenzie counted 2 GWh of commissioned cell capacity in August 2026, less than 1% of the roughly 260 GWh of storage demand in India’s 2026 tenders. It expects containers, battery packs and control software to be made in India within two to three years, cells from imported materials within two to five years, and full self-sufficiency in cells in ten to fifteen years.
Wood Mackenzie also estimates that Indian cells will cost 25 to 40% more than imported ones, and that raising Indian content from below 20% to 100% would add about 30% to the cost of a benchmark 100 MW, two-hour project.
Alongside the storage scheme, the Cabinet approved ₹2,814 crore to support processing lithium and nickel in India, through a 30% capital subsidy for two lithium and two nickel plants. Government support is moving step by step further back up the supply chain.
- 86 GWhCapacity for packs, containers and complete systems in IndiaMercom, Oct 2026
- Under 1%Indian cell capacity as a share of storage demand in 2026 tendersWood Mackenzie, Aug 2026
- 25–40%Expected extra cost of Indian cells over importsWood Mackenzie, Aug 2026
Where software fits
Indian software helps, but it will not carry a 40% bid on its own.
Software was the one part the December 2025 order named, and it is still worth getting right. India has a lot of engineering talent in it, and the large plants built so far mostly run on foreign software, so there is room for Indian energy-management software with a track record. Under a 40% rule, though, it is one part of the answer rather than the whole of it.
The order’s wording, “indigenously developed”, still has no settled test. A foreign product with an Indian logo on it is the most likely to fail a strict test. A licensed core with substantial development in India, Indian ownership of the application layer and the code kept in India is the most likely to pass. An integrator can build its own software, which takes two to three years and a working track record; license a core and develop the rest in India; or set up a joint venture with a technology partner.
In a strategy review for a storage manufacturer, an outside adviser had recommended building the software compliance programme around United States standards. The United States was not on the company’s list of target markets; India was. Moving the budget to the market where the rules gave the company an advantage turned the software from a cost into the strongest point in its investor presentation.
Routes for Indian manufacturers and integrators
Most bidders will combine routes: assemble in India now and add Indian cells as factories open.
There are three main routes to 40%. Many companies will combine them, for example assembling systems in India now while signing up for Indian cells as the new factories start.
| Route | What it takes | Where it can go wrong |
|---|---|---|
| Make the system in India around imported cells | Indian packs, containers, battery-management and energy-management systems, with power conversion assembled in India. | May fall short of 40% if the rule is measured on the battery system or names cells. |
| Buy cells from Indian factories | Supply agreements with Indian cell makers as their plants start, with the extra cost built into tender prices. | Cost and timing: Indian cells are expected to cost more, and many plants are still being built. |
| Make in India with a technology partner | Licensed designs for cells, battery-management systems or power electronics, made in India under a licence, a supply agreement or a joint venture. | Ownership of the technology, quality control and how to exit need agreeing before the first bid. |
What it means for technology companies outside India
India becomes a place to make things with a partner, not just a market to ship to.
The 40% rule makes it harder to ship finished systems into publicly funded projects, and more rewarding to make in India. Technology companies outside India, including makers of battery-management systems, power electronics, energy-management software, cell technology and production equipment, have what Indian manufacturers need to close the gap. Indian partners bring the factories, the relationships with tendering bodies, a presence in the states and the service teams.
The usual arrangements are licences with commitments to manufacture locally, supply agreements and joint ventures. Royalties and licence fees paid abroad do not count as Indian content under India’s procurement rules, which affects how a licence is priced. Each arrangement needs three things agreed before anyone signs: what the rules will count, who will own the technology, and who controls quality and production.
Timing matters. Indian manufacturers are choosing their technology partners now, while the guidelines are being written and the first tenders under the new scheme are prepared. Check what the tender requires before committing to an arrangement.
What the 40% rule means for each type of business
The rule rewards companies that make more of the battery in India.
- Indian manufacturers and integrators. Assembly alone may no longer be enough. Indian packs, battery-management systems and cell supply become what wins bids.
- Developers bidding for funded projects. Expect higher equipment costs and tighter supply of Indian parts, and build supplier commitments and the evidence file into every bid.
- Technology companies outside India. Selling finished systems into funded projects gets harder. Licences and joint ventures with Indian makers become the way in.
- Investors. Indian capacity for packs, battery-management systems and cells is likely to be in demand. The guidelines will show whether assembly or cells gain most.
What to do next
Five steps for the next two quarters.
- Map the bill of materials. Every part of the system: where it is made, what it costs and who can certify it.
- Watch for the guidelines. How the 40% is measured and which parts count. Brief your lawyers as soon as they are out.
- Choose what to make in India first. Packs, battery-management systems, power-conversion assembly and software are the nearer steps. Cells take longer.
- Line up supply and partners. Indian cells or a technology partner, with the cost built into your tender prices.
- Build the evidence file. Certificates, origin records and cost audits, ready before the first bid.
Words used in this paper
- Viability gap funding (VGF): A government grant covering part of a project’s cost, so it can be built at a price buyers will pay.
- Domestic content: The share of a project’s cost that is made or done in India.
- Energy-management software: The program that decides when the battery charges and discharges, and runs the plant.
- Battery-management system: The electronics that monitor the cells and keep them safe.
- Power conversion: The equipment that turns the battery’s direct current into grid alternating current, and back.
- Production-linked incentive (PLI): Government grants paid to factories according to how much they produce.
- GWh: Gigawatt-hour, a measure of how much energy a battery can store.
- Crore: Ten million. ₹14,500 crore is ₹145 billion.
- Distribution company (discom): The company that supplies electricity to homes and businesses in an Indian state.
- Tariff-based competitive bidding: An auction in which capacity goes to the bidders offering the lowest price for the service.
- Pumped hydro: Storage that pumps water uphill when power is cheap and lets it flow back through turbines when power is needed.
- Bill of materials: The full list of parts in a product, with their sources and costs.
- Central Electricity Authority (CEA): The Indian government body that sets technical standards for the power system.
- Statutory auditor: The auditor who signs a company’s annual accounts.
Figures and rules were checked on 9 November 2026. The guidelines for the 40% rule had not been published at that date. This is general information, not legal, tax or investment advice. Check the primary sources before you commit money.
Sources
- Prime Minister’s Office, “Cabinet approves Rs.14,500 crore Viability Gap Funding Scheme for development of 92 GWh Grid-Scale Energy Storage Systems” (4 November 2026): pmindia.gov.in
- Argus, “India approves funding for 92GWh grid-scale storage” (4 November 2026): argusmedia.com
- PV Tech, “India’s CEA proposes mandatory storage for new solar, wind projects from 2027” (4 September 2026): pv-tech.org
- TaiyangNews, “India steps up battery localization with two new schemes” (November 2026): taiyangnews.info
- pv magazine India, “India mandates 20% domestic content in battery storage projects” (31 December 2025): pv-magazine-india.com
- Mercom India, “Power Ministry mandates 20% local content requirement for VGF BESS projects”: mercomindia.com
- Energy-Storage.News, “India introduces 20% domestic content rule for viability gap funding of battery storage” (December 2025): energy-storage.news
- SolarQuarter, “India’s battery cell manufacturing faces 10–15 year gap to self-sufficiency: Wood Mackenzie” (20 August 2026): solarquarter.com
- Department of Industrial Policy and Promotion, Public Procurement (Preference to Make in India) Order 2017, revised 28 May 2018: istm.gov.in
- Nishith Desai Associates, “Public procurement framework for Make in India revised” (5 August 2024): nishithdesai.com
- Energética India, “43 GWh of BESS supported under VGF scheme with INR 9,160 Cr outlay: Power Minister” (6 August 2025): energetica-india.net
- Mercom India, “India’s downstream battery storage manufacturing capacity reaches 86 GWh” (22 October 2026): mercomindia.com
- SMM, “India’s BESS manufacturing push accelerates, but cell dependence remains a key bottleneck” (30 September 2026): news.metal.com
- Energy-Storage.News, “India adds 30GWh to VGF battery storage support scheme” (June 2025): energy-storage.news
- JMK Research, “VGF scheme expands to support 30 GWh of new standalone BESS development in India”: jmkresearch.com
- MVA Pulse, BESS tender tracker (2024–26): mvapulse.com
- pv magazine India, “Premier Energies, RCT India to form JV for 12 GWh BESS factory” (11 September 2026): pv-magazine-india.com